THIS EVENT HAS PASSED – THIS PAGE CAN BE TAKEN DOWN
Current status: Millennium is back to 'live service'.
EPMA is currently being piloted on Capel Annex ward (as at 05/01/2015)
DP calls will take place as scheduled and reconvened if necessary
SMS Updates will be sent
Planned | Status | |
DP1 – Proceed with Uptime | 25/11/2014 12:30 | passed |
DP2a – Authority to Proceed with Downtime / Prep for Downtime | 28/11/2014 12:00 | passed |
DP2b – Downtime checkpoint prior to downtime starting | 29/11/2014 02:00 | passed |
Start of RDDS (Cerner activity) | 29/11/2014 06:02 | on schedule |
Start of Cerner Build | 29/11/2014 10:32 | on schedule |
Start of Pipe cleaning (BT/Cerner + Trust) | 29/11/2014 15:52 | on schedule tested OK |
DP3a – Start Trust non-Meds Test | 29/11/2014 17:00 | passed |
ED back on + data catch up | 29/11/2014 18:45 | started 20:30 |
DP4a – Go-Live Non-Meds (Review of Output from Testing) | 29/11/2014 21:45 | passed |
DP3b – Confirm Full ePMA Build Complete, Trust able to start testing | 30/11/2014 18:30 | passed |
DP4b Go-live with Meds (after testing) | 02/12/2014 12:30 | passed |